CFA

CFA (Continuous Flight Auger) technology joins the advantages of fixed piles with the versatility of application of drilled piles. Continuous Flight Auger piles are performed with a partial soil removal, thus with a lateral soil compression that increases the final load bearing capacity. The construction procedure consists of boring the soil by means of a continuous flight auger assembled on a central hollow pipe. On completion of boring operation, auger is extracted while concrete is poured throughout the internal hollow pipe. When required, piles may be reinforced for their entire length with reinforcement cages inserted in the still wet concrete.

cfa-1cfa-2cfa-3

Features:
  • Tool Dia: 400 to 1400 mm
  • Depth: 15 to 33 m depending on soil diameter and consistency.
  • Coupling : According to the rotary torque